Installation environment of sulfur dioxide test chamber

1.The sulfur dioxide test chamber should be installed in a place where there is no direct sunlight.
 
2. Installation as close as possible to the power supply.
 
3.The sulfur dioxide test chamber is installed separately in a separate room to avoid damage to other equipment caused by corrosion gas spillage during the operation of the sulfur dioxide test chamber.
 
4.The studio should have ventilation to allow ventilation in the workroom at any time.
 
5.The studio must have 220V power (this is only for reference, according to the customer's site requirements) and pure water.
 
6.In order to stabilize the performance and function of the equipment, the sulfur dioxide test chamber should be in a working environment with a normal temperature of 15 ° C ~ 28 ° C and a relative humidity of not higher than 85%.
 
7.The ambient temperature and humidity of the installation site are strictly prohibited to change drastically.
 
8.After the sulfur dioxide test chamber is installed, the sunlight cannot directly hit the surface of the equipment.
 
9.The room should be well ventilated and the sulphur dioxide test chamber should be kept away from flammable, explosive materials and dust.
 
10. There should be tap water and pool for the convenience of the staff to clean indoors.
 
11.For ventilation, operation and maintenance, the sulfur dioxide test chamber and adjacent items or walls should have a certain space for the staff to operate. The space between the front and rear of the box should be no less than 1~1.5 meters.
 
12.There should be exhaust holes for exhaust gas from the equipment and sewers for discharging waste water.
 
For more details, please feel free to contact sales@lenpure.com